Kerala PSC Previous Years Question Paper & Answer

Title : OVERSEER GRADE III CIVIL IRRIGATION
Question Code : A

Page:8


Below are the scanned copy of Kerala Public Service Commission (KPSC) Question Paper with answer keys of Exam Name 'OVERSEER GRADE III CIVIL IRRIGATION' And exam conducted in the year 2015. And Question paper code was '204/2015'. Medium of question paper was in Malayalam or English . Booklet Alphacode was 'A'. Answer keys are given at the bottom, but we suggest you to try answering the questions yourself and compare the key along wih to check your performance. Because we would like you to do and practice by yourself.

page: 8 out of 11
Excerpt of Question Code: 204/2015

0-2
Correct Answel
Question68:-The mi
A:-40 mm
B:-50 mm
C:-75 mm
D:-100 mm
Correct Answer:- Option-B
Question69:-The effect produced by the elevation and general planning of a building is known as
A:-Elegance
B:-Roominess
C:-Prospect
D:-Aspect
Correct Answer:- Option-A
Question70:-Site plan as per N.B.C 1970 should be drawn to a scale of not less than
A:-1:200
B:-1:1000
6 00
D:-1:300
Correct Answer:-Question Cancelled
Question71:-Usual imum size of service pipe for domestic water supply is
A:-10 mm
B:-15 mm
C:-25 mm
D:-20 mm
Correct Answer:- Option-D
Question72:-As per N.B.C the minimum area of bath and WC is
ക:-2.8 “൦2
8:-1.9 "007
:-2.2 "072"
0:-1.5 "0072"
Correct Answer:- Option-A
Question73:-Shear reinforcement in R.C.C is provided to resist
A:-Vertical shear
B:-Horizontal shear
C:-Oblique shear
D:-Diagonal tension
Correct Answer:- Option-D
Question74:-A slab supported along two sides is called
A:-Overhanging slab
B:-Two way slab
C:-One way slab
D:-Cantilever slab
Correct Answer:- Option-C
Question75:-In two way slab, each side of the square mesh in length should be
A:-1/5 of the longer span
B:-1/5 of shorter span
C:-1/8 of longer span
D:-1/7 of longer span
Correct Answer:- Option-B
Question76:-Adding a thin layer of cement mortar to the surface of concrete
A:-Laitance
B:-Quartering
C:-Retempering
D:-Rendering
Correct Answer:- Option-D
Question77:-In two way slab the reinforcements in the shorter span are in the longer span.
A:-More than
B:-Less than

Option-B
um size of rainwater pipe shall be